Log Date | Log Headline | Description |
|---|---|---|
| 2019-12-02 | Building permit | Permit for 37m2 summer house |
| 2020-01-07 | Start work on foundation | Foundation work started |
| 2020-01-10 | Foundation ready | Foundation ready for log installations |
| 2020-02-18 | Logs transported to site | Sea transport to island |
| 2020-03-28 | Start of log installations | First logs installed successfully |
| 2020-05-31 | Start work on roof | First beam up |
| 2020-08-19 | Pilars in place | Supporting roof above terrass |
| 2020-08-21 | Terrass roof ready | Lists to be completed |
| 2021-02-20 | Doors installed | Both front doors in place |